Certified Associate in Project Management (CAPM) — Question 380

In which Project Cost Management process is work performance data included?

Answer options

Correct answer: D

Explanation

The correct answer is D, Control Costs, because this process involves monitoring project expenditures and performance data to ensure that the project stays within the approved budget. The other options focus on planning and estimating costs rather than utilizing actual performance data.