Certified Associate in Project Management (CAPM) — Question 371
The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?
Answer options
- A. Least cost
- B. Qualifications only
- C. Sole source
- D. Fixed budget
Correct answer: C
Explanation
The correct answer is C, Sole source, because it indicates that only one supplier can provide the required special part. The other options, such as Least cost and Fixed budget, imply competitive bidding or cost considerations, while Qualifications only focuses on the supplier's capabilities rather than exclusivity.