Which of the following is used as an input to prepare a cost management plan?

Answer options

Correct answer: D

Explanation

The correct answer, D, indicates that the project management plan provides essential information and context necessary for developing a cost management plan. While expert judgment, lessons learned, and cost estimates may also inform aspects of cost management, they do not serve as the primary input for crafting the overall plan.