Certified Associate in Project Management (CAPM) — Question 370
Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives refers to?
Answer options
- A. Operations management
- B. Project management
- C. Program management
- D. Portfolio management
Correct answer: D
Explanation
The correct answer is D, Portfolio management, which focuses on managing a group of projects and programs to align with strategic objectives. Options A, B, and C refer to specific management areas that do not encompass the broader scope of managing multiple projects and programs collectively.