Certified Associate in Project Management (CAPM) — Question 363

With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?

Answer options

Correct answer: D

Explanation

The project manager has the most direct influence over the project team as they are responsible for leading and guiding this group to achieve project goals. While suppliers, customers, and governing bodies are important stakeholders, their influence is more indirect compared to that of the project team, which is directly managed by the project manager.