During which process of Project Cost Management does a project manager produce the cost baseline?
Answer options
- A. Estimate Costs
- B. Control Schedule
- C. Determine Budget
- D. Develop Project Charter
Correct answer: C
Explanation
The correct answer is C, 'Determine Budget', as this process involves aggregating the estimated costs to establish an approved baseline for measuring project performance. Options A, B, and D are incorrect because they pertain to estimating costs, overseeing schedule management, and initiating the project, respectively, rather than establishing the cost baseline.