Certified Associate in Project Management (CAPM) — Question 362
Which is the correct hierarchy in a project environment, from most to least inclusive?
Answer options
- A. Projects, portfolios, then programs
- B. Portfolios, programs, then projects
- C. Portfolios, projects, then programs
- D. Projects, programs, then portfolios
Correct answer: B
Explanation
The correct answer is B because portfolios encompass multiple programs and projects, making them the most inclusive. Programs consist of related projects, which makes them less inclusive than portfolios but more inclusive than individual projects. Options A, C, and D incorrectly place projects or programs in a higher position than portfolios.