Certified Associate in Project Management (CAPM) — Question 296
A project team member is discussing a new project with their manager. The project is very similar to a project that was delivered last year and the scope is very well documented.
Which of the following project delivery approaches should be recommended?
Answer options
- A. Adaptive
- B. Traditional
- C. Extreme
- D. Hybrid
Correct answer: B
Explanation
The Traditional project delivery approach is the most suitable here due to the clear and well-documented scope, which aligns with the structured nature of Traditional methodologies. Adaptive approaches are better for projects with evolving requirements, while Extreme and Hybrid methods are less appropriate given the stable project parameters.