A project is composed of three phases that are implemented in parallel without affecting one another. The baselines for each individual phase have been approved by the major stakeholders, and there is a minimal ability to vary the baselines during the execution of the project.
Which methodology did the project manager adopt?
Answer options
- A. Iterative approach
- B. Predictive approach
- C. Incremental approach
- D. Hybrid approach
Correct answer: B
Explanation
The correct answer is B, the Predictive approach, as it involves planning phases with fixed baselines that are approved by stakeholders. The other options, such as Iterative and Incremental, suggest a level of flexibility and adaptation that is not present in this scenario.