Certified Associate in Project Management (CAPM) — Question 25
What is the project manager's responsibility in Project Integration Management?
Answer options
- A. Ensuring that requirements-related work is clarified in the project management plan
- B. Investing sufficient effort in acquiring, managing, motivating, and empowering the project team
- C. Combining the results in all other knowledge areas and overseeing the project as a whole
- D. Developing a strategy to ensure effective stakeholder communication
Correct answer: C
Explanation
The correct answer is C because the project manager is responsible for integrating various project elements and ensuring they work together effectively. Options A, B, and D focus on specific aspects of project management but do not capture the overarching role of integration that encompasses overseeing the project as a whole.