Certified Associate in Project Management (CAPM) — Question 26

What process group establishes project scope, refines objectives, and defines the actions necessary to attain project objectives?

Answer options

Correct answer: B

Explanation

The correct answer is B, Planning, as it focuses on establishing the project scope and defining objectives and actions needed for success. Option A, Executing, is about carrying out the planned activities, while C, Initiating, deals with starting the project, and D, Monitoring and Controlling, involves tracking progress and making adjustments.