Certified Associate in Project Management (CAPM) — Question 24
Which statement summarizes the role of the change control board?
Answer options
- A. The change control board is responsible for presenting the change for approval
- B. The change control board will analyze the change impact in terms of cost and schedule
- C. The change control board is responsible for managing the change management and configuration management systems
- D. The change control board is responsible for reviewing and approving changes to the project
Correct answer: D
Explanation
The correct answer is D because the change control board's main duty is to review and approve project changes. Options A, B, and C describe other responsibilities that may be part of the process but do not capture the board's primary role.