Certified Associate in Project Management (CAPM) — Question 244
Who identifies project requirements in the early phase of the project?
Answer options
- A. Project sponsor, business analyst, and key stakeholders
- B. Project manager, business analyst, and key stakeholders
- C. Business analyst, product team, and key stakeholders
- D. Project manager, business analyst, and project sponsor
Correct answer: A
Explanation
The correct answer is A, as the project sponsor, business analyst, and key stakeholders are typically involved in identifying requirements at the start of a project. Options B and D include the project manager, who usually plays a role in overseeing the project rather than defining initial requirements. Option C includes the product team, which may not be present in the early phases focused on requirement gathering.