Certified Associate in Project Management (CAPM) — Question 243
A product owner asked for a change in one of the requirements during the elicitation phase. What should the business analyst do?
Answer options
- A. Provide the information to the product manager for approval.
- B. Provide the information to the project manager to seek approval or rejection.
- C. Accept the modification and update the requirements traceability matrix.
- D. Reject the change as the project scope has already been defined.
Correct answer: C
Explanation
The correct answer is C because the business analyst should accept the change and update the requirements traceability matrix to reflect the new requirements. Option A and B suggest seeking approval from others, which may delay the process unnecessarily, and option D is incorrect as it dismisses the importance of adapting to changes during the project.