A product owner asked for a change in one of the requirements during the elicitation phase. What should the business analyst do?

Answer options

Correct answer: C

Explanation

The correct answer is C because the business analyst should accept the change and update the requirements traceability matrix to reflect the new requirements. Option A and B suggest seeking approval from others, which may delay the process unnecessarily, and option D is incorrect as it dismisses the importance of adapting to changes during the project.