Certified Associate in Project Management (CAPM) — Question 245
Which two of the following can be used as communication tools between the business analyst and the rest of the project team? (Choose two.)
Answer options
- A. Responsible, accountable, consult, inform (RACI) matrix
- B. Gantt chart
- C. Pareto chart
- D. Process flows
- E. Project management plan
Correct answer: A, D
Explanation
The Responsible, accountable, consult, inform (RACI) matrix helps clarify roles and responsibilities, enhancing communication among team members. Process flows visually represent the steps in a process, which aids in understanding and discussion. The other options, while useful in project management, do not specifically serve as communication tools between the business analyst and the project team.