Certified Associate in Project Management (CAPM) — Question 203

A project team has completed the sprint review and the users are impressed by the demo. However, another functionality included in the sprint that was not discussed in the review is not ready for production deployment.

What should the project team do?

Answer options

Correct answer: B

Explanation

The correct answer is B because the team should deploy the functionality that was ready and demonstrated to the users, ensuring they deliver value. Option A is incorrect as the retrospective is not meant for demos of incomplete work, while C and D are inefficient strategies that would delay delivery of completed features.