A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?

Answer options

Correct answer: D

Explanation

The correct answer is D because the critical path is defined as the longest sequence of dependent tasks that determines the shortest completion time of the project. Option A is incorrect because it refers to leveled resources, which are not relevant to finding the critical path. Option B is wrong as it talks about float duration, which is not a determining factor for the critical path. Option C misinterprets the concept, as crashing a schedule is about shortening duration, not identifying the critical path.