Certified Associate in Project Management (CAPM) — Question 202
A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?
Answer options
- A. Identify the path through the schedule with leveled resources and the shortest duration.
- B. Identify the tasks with float duration, which do not impact the duration of the project.
- C. Identify the crashed project schedule to find the shortest duration to complete the project.
- D. Identify the longest activity path in the schedule with the shortest possible duration.
Correct answer: D
Explanation
The correct answer is D because the critical path is defined as the longest sequence of dependent tasks that determines the shortest completion time of the project. Option A is incorrect because it refers to leveled resources, which are not relevant to finding the critical path. Option B is wrong as it talks about float duration, which is not a determining factor for the critical path. Option C misinterprets the concept, as crashing a schedule is about shortening duration, not identifying the critical path.