Certified Associate in Project Management (CAPM) — Question 188
How can working in iterations increase the quality of the product being built?
Answer options
- A. The project manager has more time to document goals in advance.
- B. Requirements are frequently clarified by users of the product.
- C. Teams have to do less planning and focus more on quality.
- D. Less testing is required since it is done at the end of the project.
Correct answer: B
Explanation
The correct answer is B because working in iterations allows for ongoing feedback and clarification from users, which helps ensure that the product meets their needs. Options A, C, and D are incorrect as they suggest that less planning or testing is beneficial, which can actually compromise the overall product quality.