Certified Associate in Project Management (CAPM) — Question 189

An international company that is starting to practice an adaptive approach has several development teams located globally. They are having problems with multiple time zones and repetitive project schedule slippage.

What effective tools should the project teams use to collaborate?

Answer options

Correct answer: C

Explanation

The correct answer is C because adopting an iterative development approach and conducting virtual meetings can help bridge time zone gaps and facilitate ongoing collaboration. Options A and B do not address the root issues of time zone challenges and project delays, while D may not be feasible for globally distributed teams.