Certified Associate in Project Management (CAPM) — Question 155
Which of the following can a project manager conduct if they have a stakeholder who is unresponsive and/or unsupportive?
Answer options
- A. Communication style assessment
- B. Push communications
- C. Pull communications
- D. Interactive communications
Correct answer: A
Explanation
A Communication style assessment is essential for understanding how to engage unresponsive stakeholders effectively. Push communications, Pull communications, and Interactive communications are communication methods but do not directly address the issue of stakeholder engagement as the assessment does.