Certified Associate in Project Management (CAPM) — Question 154
An executive sponsor wants to be briefed on how the product will change over time. Which document should the business analyst use to prepare their presentation?
Answer options
- A. Project charter
- B. Project management plan
- C. Product roadmap
- D. Product requirement
Correct answer: C
Explanation
The correct answer is C, the Product roadmap, as it outlines the planned evolution and changes of the product over time. The other options do not provide a comprehensive view of future product changes; the project charter focuses on the project’s objectives, the project management plan details how the project will be executed, and the product requirement specifies what the product must do.