Certified Associate in Project Management (CAPM) — Question 157
A project has encountered some difficulties that will impact the project management plan and the project management process. Which two actions should the project manager take? (Choose two.)
Answer options
- A. Perform quality management.
- B. Submit a change request.
- C. Perform a risk analysis.
- D. Perform integrated change control.
- E. Perform integrated project management.
Correct answer: B, D
Explanation
The correct actions are B and D because submitting a change request is necessary to formally address the impact on the project plan, while integrated change control is essential for managing changes effectively. Options A, C, and E, while important aspects of project management, do not directly address the immediate need to revise the project plan due to encountered difficulties.