Certified Associate in Project Management (CAPM) — Question 124
Which three of the following interpersonal skills does a project manager rely on when developing the project management plan? (Choose three.)
Answer options
- A. Conflict management
- B. Facilitation
- C. Interviews
- D. Meeting management
- E. Focus groups
Correct answer: A, B, D
Explanation
The correct answers, A, B, and D, are essential for effectively managing team dynamics and ensuring successful communication throughout the project. While interviews and focus groups (C and E) can provide valuable information, they are not primarily interpersonal skills that facilitate the development of the project management plan.