Certified Associate in Project Management (CAPM) — Question 125

At the end of the third iteration, the project team gathers to discuss the stories to be implemented in the next iteration. What should the team do during this session?

Answer options

Correct answer: D

Explanation

The correct answer is D because planning the backlog involves estimating and reprioritizing user stories based on the latest insights, which is essential for effective iteration planning. Option A focuses on analysis rather than planning, B suggests a spike that may not be necessary if the information is already clear, and C emphasizes risk discussion instead of backlog organization.