Certified Associate in Project Management (CAPM) — Question 119

What are the three components of a work breakdown structure (WBS) dictionary? (Choose three.)

Answer options

Correct answer: C, D, E

Explanation

The correct components of a WBS dictionary are the List of resources (C), Description of work (D), and Acceptance criteria (E). These elements provide detailed information necessary for project execution, while the List of stakeholders (A) and Description of risks (B) are not standard components of a WBS dictionary.