Certified Associate in Project Management (CAPM) — Question 117
A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?
Answer options
- A. Resource management plan and cost baseline
- B. Resource management plan and lessons learned register
- C. Resource management plan and procurement management plan
- D. Resource management plan and preassignment
Correct answer: A
Explanation
The correct answer is A because after onboarding resources, the project manager needs to update the Resource management plan to reflect the newly assigned resources and the cost baseline to account for any changes in budget due to these resources. The other options include components that do not require updating immediately after onboarding, such as lessons learned register or procurement management plan.