Certified Associate in Project Management (CAPM) — Question 116
An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project.
What data should be included in this information radiator?
Answer options
- A. Key performance indicators (KPIs) and baseline
- B. Product and sprint backlog
- C. Burndown and burnup charts
- D. Increments and bottlenecks
Correct answer: B
Explanation
The correct answer is B, as the product and sprint backlog are crucial components for tracking tasks and managing the work in a scrum environment. While options A, C, and D provide useful information, they do not specifically represent the primary data elements necessary for managing the flow of work in this context.