Certified Associate in Project Management (CAPM) — Question 111
Which of the following is a goal of the project charter?
Answer options
- A. Detail requirements for the project tasks.
- B. List all tasks the team should perform in the project.
- C. Empower the project manager to manage the project.
- D. Develop a business case to support the project.
Correct answer: C
Explanation
The correct answer is C because the project charter is designed to grant the project manager the authority to lead the project effectively. Options A and B are incorrect as they focus on detailing tasks and requirements rather than the authority of the project manager. Option D, while related to project justification, does not specifically relate to the role of the project charter.