Certified Associate in Project Management (CAPM) — Question 112
An adaptive project team is meeting for the first time and deciding on the project management approach. After defining the project artifacts, one team member argues that the events are missing. The scrum master coaches the team to complete the planning.
Which two of the following elements should be included? (Choose two.)
Answer options
- A. Sprint backlog
- B. Increments
- C. Product backlog
- D. Sprint retrospective
- E. Daily scrum
Correct answer: D, E
Explanation
The correct answers are D and E because the Sprint retrospective and Daily scrum are key events in the Scrum framework that facilitate continuous improvement and daily synchronization. Options A, B, and C refer to artifacts rather than events, making them inappropriate choices for this context.