Certified Associate in Project Management (CAPM) — Question 110
A business case is being assembled. Which two elements are necessary to complete this process? (Choose two.)
Answer options
- A. Requirements traceability matrix
- B. Risk register
- C. Project management plan
- D. Product roadmap
- E. Business goals and objectives
Correct answer: D, E
Explanation
The correct answers, D and E, are critical as the product roadmap outlines the strategic direction and the business goals and objectives define what the organization aims to achieve. The other options, while useful in project management, do not directly contribute to the establishment of a business case.