Certified Associate in Project Management (CAPM) — Question 10
Select three processes that are associated with Project Schedule Management? (Choose three.)
Answer options
- A. Define Activities
- B. Plan Resource Management
- C. Estimate Activity Durations
- D. Develop Schedule
- E. Acquire Resources
Correct answer: A, C, D
Explanation
The correct options, A, C, and D, are directly related to Project Schedule Management as they involve defining activities, estimating how long tasks will take, and developing the overall project schedule. Options B and E focus on resource management and acquisition, which are not specific to schedule management.