In an adaptive project environment, which action helps the project manager ensure that the team is comfortable with charges?
Answer options
- A. Having control over the planning and delivery of the products without delegating decisions
- B. Giving access to information to the team and frequent team checkpoints
- C. Selecting different team members to take the project manager role during reviews with stakeholders
- D. Asking the control change board to approve changes before notifying the team
Correct answer: B
Explanation
Option B is correct because giving the team access to information and holding frequent check-ins fosters transparency and comfort with changes. Option A restricts decision-making and may create discomfort, while options C and D do not directly address the team's comfort with changes.