Certified Associate in Project Management (CAPM) — Question 9
During what project management process does the project team begin identifying risks?
Answer options
- A. Initiating
- B. Planning
- C. Executing
- D. Monitoring and Controlling
Correct answer: B
Explanation
The correct answer is B, as risk identification occurs during the Planning phase when the project team assesses potential issues that could impact project objectives. Options A, C, and D represent other phases where risk management is not the primary focus; Initiating involves defining the project, Executing is about implementation, and Monitoring and Controlling focuses on tracking project progress.