Microsoft Dynamics 365 Field Service — Question 198
You are a dispatcher for Dynamics 365 Field Service. You schedule a resource to a work order using the schedule board.
The resource appears available, but informs you they put in a Time Off Request for that period.
Which two options are potential reasons why the resource appears available, but informs you they are not available? Each answer represents a complete solution.
Answer options
- A. The schedule board is not syncing with the resource’s schedule
- B. Time off request is Inactive
- C. Time off request has not been approved
- D. The time zone for the resource is set incorrectly
Correct answer: C, D
Explanation
The correct answer includes C, as an unapproved Time Off Request would not be recognized by the system, allowing the resource to appear available. D is also correct because an incorrect time zone setting could lead to discrepancies in availability. A and B are not valid because they do not directly explain the resource's unavailability despite appearing available.