Managing Projects and Portfolios with Microsoft PPM — Question 4
This question requires that you evaluate the underlined text to determine if it is correct.
Cost resources affect the schedule when theyre assigned to tasks.
Review the underlined text. If it makes the statement correct, select "No change is needed". If the statement is incorrect, select the answer choice that makes the statement correct.
Answer options
- A. No change is needed.
- B. Work resources.
- C. Material resources.
- D. Budget work resources.
Correct answer: B
Explanation
The highlighted text is incorrect because cost resources do not directly affect the schedule like work resources do. Work resources are the ones that, when assigned to tasks, influence the timeline of the project.