Managing Projects and Portfolios with Microsoft PPM — Question 5

An organization uses Microsoft PPM to manage projects. The organization tracks all projects by collecting time on tasks on a daily basis.
You need to ensure that resources can enter their time on tasks.
Which three actions should you take? Each correct answer presents part of the solution.

Answer options

Correct answer: A, B, C

Explanation

The correct answers A, B, and C are necessary to allow resources to input their time effectively. Option A sets the appropriate tracking method for capturing hours worked, option B ensures that hours are reported daily, and option C removes the restriction on project managers that could hinder this process. Option D enforces a reporting method that may not align with the desired daily tracking, and option E does not directly enable the functionality needed for resources to report time.