ITIL 4 Foundation — Question 85
Which statement about change authorities is CORRECT?
Answer options
- A. Change authorities are only required for authorizing emergency changes
- B. Change authorities are assigned when each change is deployed
- C. Change authorities are only required for authorizing normal changes
- D. Change authorities are assigned for each type of change and change model
Correct answer: D
Explanation
The correct answer is D because change authorities are indeed assigned based on the type of change and the corresponding change model to ensure proper governance. Options A, B, and C are incorrect as they incorrectly limit the scope of change authorities to specific types of changes, neglecting their broader role in overall change management.