ITIL 4 Foundation — Question 222

Which practice balances management of risk with maximizing throughput?

Answer options

Correct answer: D

Explanation

Change enablement is designed to manage risks associated with changes while ensuring that throughput is maximized. Problem management and incident management focus more on resolving issues rather than balancing risk with throughput. Continual improvement, while important, does not specifically address the balance of risk and throughput like change enablement does.