Certified Business Analysis Professional (CBAP) — Question 274

Which of the following communicates from the program-level perspective "" a clear understanding and statement of the technical objectives and the end products, services, or results of the work to be performed?

Answer options

Correct answer: D

Explanation

The Program charter is essential because it outlines the technical objectives and expected deliverables of the program, providing a foundational understanding for all stakeholders. The Scope statement and Preliminary scope statement are more focused on specific projects rather than the overarching program. The Program work breakdown structure is a tool for organizing tasks, but it does not communicate the technical objectives or end products directly.