What combination of information on a Work Order is used to create a histogram in the Graphical Scheduling application?
Answer options
- A. Craft/Skill Level Quantity and Hours
- B. Labor and Crew Hours
- C. Craft Quantity and Hours
- D. Crew Work Group Quantity and Hours
Correct answer: D
Explanation
The correct answer is D because the Crew Work Group Quantity and Hours provide the necessary data to visualize resource allocation effectively in a histogram. The other options either focus on different aspects of labor or skills that do not directly relate to the creation of a histogram in this specific context.