IBM MQ v9.2 System Administration — Question 54

What combination of information on a Work Order is used to create a histogram in the Graphical Scheduling application?

Answer options

Correct answer: D

Explanation

The correct answer is D because the Crew Work Group Quantity and Hours provide the necessary data to visualize resource allocation effectively in a histogram. The other options either focus on different aspects of labor or skills that do not directly relate to the creation of a histogram in this specific context.