IBM MQ v9.2 System Administration — Question 55
In the Manage Inventory Work Center a pick list can be created, its initial status is Entered. Which three actions will cause the status to change to In Progress? (Choose two.)
Answer options
- A. Picked
- B. Restocked
- C. Prepared
- D. Issued
- E. Staged
- F. Returned
Correct answer: A, E
Explanation
The correct answers are A (Picked) and E (Staged) because both actions indicate that the items are in the process of being handled, thus changing the status to In Progress. The other options, such as B (Restocked), C (Prepared), D (Issued), and F (Returned), do not indicate that the pick list is actively being processed.