Certified Scrum Master (CSM) – GAQM — Question 73

Which of the following is NOT part of the Sprint?

Answer options

Correct answer: A

Explanation

The correct answer is A because releasing the product to customers typically happens after multiple Sprints, not at the end of each individual Sprint. Options B, C, and D correctly describe aspects of the Sprint process, focusing on goals and timing related to the Sprint itself.