Certified Scrum Master (CSM) – GAQM — Question 74
You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information:
Sprint 1: 10 pontos -
Sprint 2: 11 pontos -
Sprint 3: 15 pontos -
Sprint 4: 14 pontos -
Sprint 5: 15 pontos -
Sprint 6: 10 pontos -
The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?
Answer options
- A. 6
- B. 5
- C. 4
- D. 3
Correct answer: B
Explanation
To find the average points completed per Sprint, sum the points from all Sprints (10 + 11 + 15 + 14 + 15 + 10 = 75) and divide by the number of Sprints (6), resulting in an average of 12.5 points per Sprint. To finish the remaining 42 story points, divide 42 by the average of 12.5, which is approximately 3.36, meaning 4 Sprints are needed, but considering the options, 5 is the correct choice as it ensures completion.