What does the Scrum Development Team attempt to develop at every Sprint?
Answer options
- A. A product that is ready for customer delivery
- B. A completed Sprint Backlog
- C. A product that is ready for QA and/or QC testing
- D. A product increment that is potentially-ready for customer delivery
Correct answer: D
Explanation
The correct answer is D because the Scrum Development Team aims to produce a product increment that is potentially shippable at the end of each Sprint. Options A, B, and C do not accurately reflect the Scrum framework's focus on delivering a potentially releasable increment rather than just readiness for delivery, QA, or completion of the backlog.