Certified Scrum Master (CSM) – GAQM — Question 72

What does the Scrum Development Team attempt to develop at every Sprint?

Answer options

Correct answer: D

Explanation

The correct answer is D because the Scrum Development Team aims to produce a product increment that is potentially shippable at the end of each Sprint. Options A, B, and C do not accurately reflect the Scrum framework's focus on delivering a potentially releasable increment rather than just readiness for delivery, QA, or completion of the backlog.