Certified Scrum Master (CSM) – GAQM — Question 66
Which three questions are answered by all Development Team members at the Daily Scrum? (Choose three)
Answer options
- A. What work am I going to do today?
- B. Why were you late?
- C. What impediments are in the way of my accomplishing my work?
- D. What work did I do yesterday?
- E. How is the Sprint proceeding?
Correct answer: A, C, D
Explanation
The correct answers A, C, and D focus on the work progress and impediments, aligning with the Daily Scrum's purpose of synchronization and planning. Option B is irrelevant as personal lateness does not pertain to the team's daily updates, while option E, although related to the Sprint, does not directly address individual contributions or challenges.