Certified Scrum Master (CSM) – GAQM — Question 67

The Sprint Goal is selected before the Sprint Backlog is created.

Answer options

Correct answer: A

Explanation

The correct answer is A because the Sprint Goal serves as a guiding objective for the team and must be established before the items are selected for the Sprint Backlog. Option B is incorrect as it suggests the opposite, which contradicts the Scrum framework principles.