Certified Scrum Master (CSM) – GAQM — Question 65
Which of the following might the Scrum Team discuss during a Sprint Retrospective?
Answer options
- A. Methods of communication
- B. The way the Scrum Team does Sprint Planning
- C. Skills needed to improve the Development Team's ability to deliver
- D. Its Definition of Done
- E. All of the above
Correct answer: E
Explanation
The correct answer is E because all the mentioned topics are valid discussion points that can help the Scrum Team reflect on their processes and improve. Options A, B, C, and D are specific elements that could be analyzed, but they are not exhaustive on their own, making E the most comprehensive choice.