Certified Scrum Master (CSM) – GAQM — Question 32

Under what circumstances should the Product Backlog be reprioritized?

Answer options

Correct answer: D

Explanation

The correct answer is D because the Product Owner is responsible for managing the Product Backlog and should update its priorities as new information arises. Options A, B, and C incorrectly limit the reprioritization to specific times, which does not align with Agile principles that advocate for continuous improvement and flexibility.