Certified Scrum Master (CSM) – GAQM — Question 31
From the activities given, which is the latest step in sequence of the Scrum framework?
Answer options
- A. Daily scrum
- B. Sprint retrospective
- C. Sprint review
- D. Sprint planning
Correct answer: B
Explanation
The Sprint retrospective is the final activity in the Scrum framework, occurring after the Sprint review to reflect on the past sprint and identify improvements. The Daily scrum is a daily check-in, Sprint review presents the work completed, and Sprint planning sets up the upcoming sprint, all happening before the retrospective.