Certified Scrum Master (CSM) – GAQM — Question 30

What is the maximum duration of each Sprint planning meeting section?

Answer options

Correct answer: C

Explanation

The correct answer is C, which states that each section of the Sprint planning meeting can last up to 4 hours. Other options like A, B, D, and E represent shorter time frames that do not comply with the maximum duration guidelines established for Sprint planning meetings.